Cooling and Heating Energy Centre for Two High-Rise Buildings
Construction of a Complete Cooling and Heating Energy Centre

Country: Austria

City: Vienna

Facility: Two high-rise buildings

Project: Construction of a cooling and heating energy centre
(completed in 3 months instead of the originally planned 6 months)

Scope of work:

  • Installation of a heat pump system
  • Integration of Danube water, geothermal ground probes and air as heat sources
  • Fabrication and installation of the energy centre
  • Complete system integration

As part of the project, we delivered the complete cooling and heating energy centre for two high-rise buildings in Vienna. The works were successfully completed within just 3 months instead of the originally planned 6-month construction period, while still meeting the required deadline.

The buildings’ energy supply is provided by seven high-capacity heat pumps combining multiple energy sources: water from the Danube, geothermal ground probes and ambient air. This combination enables the system to provide highly efficient, sustainable and reliable operation for both high-rise buildings.

More references